Step  | Action  | Value(s)  | Yes  | No  | 
|---|---|---|---|---|
1  | Was the Lighting Systems Diagnostic System Check performed?  | --  | Go to Step 2  | |
2  | 
 Does all of the incandescent lighting for INC DIM 2 light?  | --  | Go to Step 3  | Go to Step 5  | 
3  | Inspect CKT 150 (BLK) for an open. Refer to Testing for Continuity in Wiring Systems. Is CKT 150 OK?  | --  | Go to Step 4  | Go to Step 7  | 
4  | Replace the headlamp switch. Refer to Headlamp Switch Replacement in Lighting Systems. Is the headlamp switch replacement complete?  | --  | Go to Step 8  | --  | 
5  | Inspect CKT 328 (PPL) for an open. Refer to Testing for Continuity in Wiring Systems. Is CKT 328 OK?  | --  | Go to Step 6  | Go to Step 7  | 
6  | Replace the instrument cluster. Refer to Instrument Cluster Replacement in Instrument Panel, Gauges and Console. Is the instrument cluster replacement complete?  | --  | Go to Step 8  | --  | 
7  | Repair the suspect wiring. Refer to Wiring Repairs in Wiring Systems. Is the repair complete?  | --  | Go to Step 8  | --  | 
8  | Operate the system in order to verify the repair. Did you correct the condition?  | --  | System OK.  | Go to Step 2  |