Operational Test
- Apply the parking brake.
 
- Block the wheels.
 
Remove the differential lock relay valve. Refer to 
Differential Lock Relay Valve Replacement 
.
- Install an air pressure gage in a common control and supply air  line
  connected to the control and supply ports of the differential lock relay   valve.
 
- Install an air pressure gage into the delivery port of the differential
   lock relay valve.
 
- Gradually apply air pressure to the common control and supply  line. As
  the pressure increases, observe the two air pressure gages.
 
| 5.1.  | Note the common control and supply line air pressure gage when  air pressure
  is delivered to the delivery port. | 
 
| 5.2.  | The common control and supply line inlet pressure should be at  290 kPa
  (42 psi) when air pressure is provided to the delivery   port of the differential
  lock relay valve. | 
 
| 5.3.  | If the test does not result in the above conditions, repair or  replace
  the differential lock relay valve. | 
 
- Slowly reduce the common control and supply line inlet air pressure. 
  As the pressure decreases, observe the two air pressure gages.
 
| 6.1.  | Note the common control and supply line air pressure gage when  air pressure
  from the delivery port is exhausted from the exhaust port. | 
 
| 6.2.  | The common control and supply line inlet pressure should be at  193 kPa
  (28 psi) when air pressure is vented through the exhaust   port. | 
 
| 6.3.  | If the test does not result in the above conditions, repair or  replace
  the differential lock relay valve. | 
 
- Remove the air pressure gage from the delivery port of the differential
   lock relay valve.
 
- Remove the air pressure gage in a common control and supply air  line
  connected to the control and supply ports of the differential lock relay   valve.
 
- Install the differential lock relay valve. Refer to 
Differential Lock Relay Valve Replacement 
.
 
Air Leakage Test
- Apply the parking brake.
 
- Block the wheels.
 
- Start the engine. Charge the air system to the air compressor  governor
  cutout point.
 
- Stop the engine.
 
- Switch the differential lock control valve lever to the ON position. 
 
- Inspect the supply, control and delivery ports for air leaks using  a
  soap solution. Air leakage is not allowed. If any leaks are present, repair   or
 replace  the differential lock relay valve.
 
- Inspect the exhaust port for air leaks using a soap solution.  A slight
  bubble leakage is allowed. If air leakage is excessive, repair or   replace the
differential   lock relay valve.
 
- Drain all of the air reservoirs. Refer to 
Draining Reservoirs 
.
 
- Remove the supply and control air lines from the differential  lock relay
  valve. Refer to Air Brakes.
 
- Install an auxiliary common air supply and control line into the  differential
  lock relay valve.
 
- Remove the delivery port air line from the differential lock relay  valve.
 
- Install a plug into the delivery port of the differential lock  relay
  valve.
 
- Apply 69 kPa (10 psi) of air pressure to the auxiliary 
  common air supply and control line.
 
- Inspect the exhaust port for air leakage. Air leakage less than  a 25.4 mm
  (1.0 in) bubble in 5 seconds is acceptable.
 
- If the air leakage is too much, repair or replace the differential  lock
  relay valve.
 
- Remove the air pressure from the auxiliary common air supply and  control
  line.
 
- Remove the plug from the delivery port of the differential lock  relay
  valve.
 
- Install the delivery port air line into the differential lock  relay valve.
 
- Install the supply and control air lines into the differential  lock relay
  valve.
 
- Start the engine. Charge the system to the air compressor governor  cutout
  point.
 
- Stop the engine.
 
- Inspect for air leaks using a soap solution.
 
- Remove the wheel blocks.