- Remove the 
J 21366 
 .
 
- Install an engine hoist to the 
J 41798 
 .
 
- Remove the engine from the engine stand.
 
- Install the engine.
 
- Mate the engine to the transmission. 
 
- Remove the floor jack from under the transmission for support.
 
Notice: Refer to Fastener Notice in the Preface section.
- Install the 3 upper transmission bolts/studs.
 
Tighten
Tighten the bolts/studs to 50 N·m (37 lb ft).
- Raise the vehicle.
 
- Install the lower transmission bolt/studs.
 
Tighten
Tighten the bolts/studs to 50 N·m (37 lb ft).
- Install the transmission bolt and stud on the right side.
 
Tighten
Tighten the bolts/studs to 50 N·m (37 lb ft).
- Install the transmission oil level indicator tube.
 
- Install the transmission oil level indicator tube nut.
 
Tighten
Tighten the nut to 10 N·m (89 lb ft).
- Install the torque converter bolts.
 
Tighten
Tighten the bolts to 60 N·m (44 lb ft).
- Install the 3 bracket bolts to both the right and the left sides of the frame engine mount.
 
Tighten
Tighten the bolts to 50 N·m (37 lb ft).
- Install the catalytic converter. Refer to 
Catalytic Converter Replacement
 .
 
- Lower the vehicle.
 
- Remove 
J 41798 
 .
 
- Install the ignition coils, as required. Refer to 
Ignition Coil Replacement
 .
 
Tighten
Tighten the bolts to 8 N·m (71 lb in).
- Install the auxiliary heater inlet and outlet hoses/pipes to the water pump using
the 
J 38185 
 .
 
- Connect the auxiliary heater inlet and outlet hose/pipe assembly to the heater water shutoff valve pipes.
 
- Install the outlet hose to the water outlet using the 
J 38185 
 .
 
- Install the inlet hose to the water outlet using the 
J 38185 
 .
 
- Position the bracket with generator to the engine.
 
- Install the generator bracket bolts.
 
Tighten
Tighten the bolts to 50 N·m (37 lb ft).
- Install the generator cable to the generator, perform the following procedure:
 
| 25.1.  | Install the generator cable. | 
 
| 25.2.  | Install the generator cable nut to the terminal stud. | 
 
Tighten
Tighten the nut to 9 N·m (80 lb in).
| 25.3.  | Slide the boot down covering the terminal stud. | 
 
- Gather all branches of the engine wiring harness and position the harness over the engine.
 
- Raise the vehicle. 
 
- Connect the A/C compressor electrical connector.
 
- Install the battery cable channel to the oil pan.
 
- Install the battery cable channel bolt.
 
Tighten
Tighten the bolt to 12 N·m (106 lb in).
- Install the starter. Refer to 
Starter Motor Replacement
 .
 
- Install the ground terminal bolts (2, 4).
 
Tighten
Tighten the bolt to 25 N·m (18 lb ft).
- Lower the vehicle.
 
- Install the retaining clip (1) to the cylinder head.
 
- Connect the A/C pressure switch electrical connector (2).
 
- Install the retaining clips to the brackets.
 
- Install the ground terminal bolt (2).
 
Tighten
Tighten the bolt to 25 N·m (18 lb ft).
- Connect the ECT sensor (1).
 
- Install the rear auxiliary A/C compressor pipe nut and bolt (2, 5).
 
Tighten
Tighten the nut/bolt to 20 N·m (15 lb ft).
- Connect the rear auxiliary A/C compressor pipe fitting (7).
 
Tighten
Tighten the nut to 16 N·m (12 lb ft).
- Install the A/C compressor hose. Refer to 
Compressor Hose Assembly Replacement
 .
 
- Connect the following electrical connectors:
 
| •  | Oil pressure sensor (1) | 
 
| •  | Camshaft position (CMP) sensor (4) | 
 
- Install the intake manifold. Refer to 
Intake Manifold Replacement
 .
 
- Install the wheel drive shafts. Refer to 
Wheel Drive Shaft Replacement
 .
 
- Install the front differential drive axle, if equipped with 4WD. Refer to 
Differential Carrier Assembly Replacement
 .
 
- Install the radiator support brace. Refer to 
Radiator Support Diagonal Brace Replacement
 .
 
- Install the radiator. Refer to 
Radiator Replacement
 .
 
- Recharge the refrigerant. Refer to 
Refrigerant Recovery and Recharging
 .
 
- Connect the negative battery cable. Refer to 
Battery Negative Cable Disconnection and Connection
 .
 
- Prelube the engine. Refer to 
Engine Prelubing
 .
 
- Perform the CKP system variation learn procedure. Refer to 
Crankshaft Position System Variation Learn
 .
 
- Install the hood. Refer to 
Hood Replacement
 .
 
Important: After an overhaul, the engine should be tested. Use the following procedure after the engine is installed in the vehicle.
- Test the vehicle using the following procedure:
 
| 53.1.  | Disable the ignition system. | 
 
| 53.2.  | Crank the engine several times. Listen for any unusual noises or evidence that parts are binding. | 
 
| 53.3.  | Enable the ignition system. | 
 
| 53.4.  | Start the engine and listen for unusual noises. | 
 
| 53.5.  | Check the vehicle oil pressure gauge or light and confirm that the engine has acceptable oil pressure. | 
 
| 53.6.  | Run the engine speed at about 1,000 RPM until the engine has reached normal operating temperature. | 
 
| 53.7.  | Inspect for fuel, oil and/or coolant leaks while the engine is running. | 
 
- Install the intake manifold sight shield. Refer to 
Upper Intake Manifold Sight Shield Replacement
 .