Step  | Action  | Yes  | No  | 
|---|---|---|---|
1  | Did you review the Charging System Description and the Charging System Circuit Description and perform the necessary inspections?  | Go to Step 2  | |
2  | Verify that the charge indicator is always on. Is the charge indicator always on?  | Go to Step 3  | Go to Testing for Intermittent Conditions and Poor Connections in Wiring Systems  | 
3  | 
 Does the charge indicator light?  | Go to Step 5  | Go to Step 4  | 
4  | Repair or replace the generator. Refer to Generator Replacement and Generator Overhaul . Is the repair complete?  | Go to Step 10  | --  | 
5  | 
 Does the charge indicator light?  | Go to Step 7  | Go to Step 6  | 
6  | Replace the DRL control module. Refer to Daytime Running Lights (DRL) Control Module Replacement in Lighting Systems. Is the repair complete?  | Go to Step 10  | --  | 
7  | Test for a short to ground in the WHT/RED wire between the instrument panel cluster and the generator. Is a short to ground present?  | Go to Step 8  | Go to Step 9  | 
8  | Repair the short. Refer to Wiring Repairs in Wiring Systems. Is the repair complete?  | Go to Step 10  | --  | 
9  | Repair or replace the instrument cluster printed circuit. Is the repair complete?  | Go to Step 10  | --  | 
10  | Operate the system in order to verify the repair. Did you correct the condition?  | System OK  | Go to Step 3  |